近年来,在框架结构现浇梁板施工中,有些施工单位采取先浇肋梁至板底,然后拆除梁侧模,支设楼(屋)面模板,绑扎板筋,再进行二次浇筑的方法,以增加模板的周转利用。笔者认为,这种施工方法不利于提高工程质量,不宜采用。(1)施工缝留置与规范相悖《混凝土结构工程施工及验收规范》(GB50204—92)规定:“梁和板宜同时浇筑混凝土(梁高大于1m者除外)”,“柱施工缝留置在基础的顶面、梁或吊车梁牛腿的下面、吊车梁的上面、无梁楼板柱帽的下面。”在一般框架结构中,梁的高度大多在1m以内,少数梁高超过1m,因此,梁板分二次浇筑是不符合规范要求的。(2)施工缝留置不当对柱的影响
In recent years, in the construction of cast-in-place beam and frame of frame structures, some construction units have taken the first step of pouring rib beams to the bottom of the plate, and then dismantle the beam side molds, support the building (house) surface form, bind the plate reinforcements, and then perform secondary pouring. Method to increase the turnover of the template. The author believes that this construction method is not conducive to improving the quality of the project and should not be used. (1) Construction indulgence shall be in accordance with the code “Construction and Acceptance Criteria for Concrete Structure Engineering” (GB50204-92) stipulates: “When beams and slabs are to be poured at the same time (except when the beam height is greater than 1m)”, “column construction joints are left on the foundation. The top of the beam, the top of the beam or crane beam, the top of the crane beam, the bottom of the beamless floor column cap." In the general frame structure, the beam height is mostly within 1m, and a few beam heights are over 1m. Therefore, the beam The secondary pouring of the board is not in compliance with the requirements of the specification. (2) Improper retention of construction joints on the column