第二讲 X矿中央水泵房施工组织设计(试例) 一、工程概况 该矿为立井开拓,对角式通风,东西两翼各有一出风立井。现副井已施工到底,并已改装为600毫米轨距、一吨矿车、双车单层临时双罐笼提升。主井井筒正在施工。西风井已到底,尚未与主副井贯通。泵房北侧中央变电所及通道将完工。中央变电所通路与副井重车道相通。水泵房的南侧为泵房通路,尚未开工。泵房硐室的两端是管子道和通风道,分别和副井、主井连通,均未施工。
Lecture X X Central Construction Design of Pumping House (Example) I. Project Overview The mine is a vertical shaft opening up, diagonal ventilation, east and west wings have a wind shaft. The existing auxiliary well has been under construction to the end and has been converted to 600 mm gauge, a ton of tub, twin twin temporary cage upgrade. The main shaft is under construction. Westerly wells in the end, not yet with the main shaft pass. The northern side of the pumping station and the central substation will be completed. The central substation access and auxiliary shaft heavy lane interlinked. The southern side of the pump room for the pump room access, not yet started. At both ends of the pump room chamber are pipelines and ventilation ducts, which are respectively connected with auxiliary wells and main wells, and have not been constructed.