在阐述淮北矿业(集团)有限责任公司涡阳矿区总体规划和蔡楼站现状的基础上,预测蔡楼站未来运量,结合涡北选煤厂的原煤入洗和精煤、中煤外运通道情况,分析空重车的到达、卸车、装车和发送情况,提出蔡楼站改扩建工程的2个方案,经过方案的优缺点分析和技术经济比选,建议采用方案Ⅰ,即将车站扩建为3个场,新建Ⅲ场(到发场)与既有Ⅰ场(到发场)、Ⅱ场(装卸场)纵列布置。
On the basis of elaborating the general planning of Qiuyang mining area and the status quo of Cai Lou Station in Huaibei Mining (Group) Co., Ltd., the future traffic volume of Cai Lou Station is predicted. Combined with the raw coal washing and coal blending at the Vortex North Coal Preparation Plant, Channel situation, analysis of empty heavy truck arrival, unloading, loading and sending situation, proposed Cai Lou station expansion project 2 programs, after the program analysis of advantages and disadvantages and technical and economic comparison, the proposed program I, the station expansion For the 3 field, the new Ⅲ field (to the field) and the existing field Ⅰ (to the field), Ⅱ field (loading and unloading) column arrangement.