中亚天然气管道工程为双管线平行敷设,管道规格为Ф1067mm,按等级分为15.9mm和19.1mm两种壁厚,管线间距30m,作业带总宽度72m。其中1096桩-1097桩施工段,长892米,该地段地表植被茂盛,常年有地表水,淤泥层较厚,渗透性差,导致施工设备进场困难、管材无法运输、管沟不易成型。经过调研和反复现场勘察,确定的总体施工方案为:挖明沟排水,作业带晾晒,分段组对焊接,漂管就位,压载下沟。本文介绍了该方案的具体施工工艺。工程实践表明,这种方法成功解决了沼泽地段管道施工的实际困难,在施工进度、质量和成本上都取得了满意的结果。可为类似地区的管道施工提供有益的借鉴。
Central Asia natural gas pipeline project laid parallel to the double pipelines, pipe specifications for Ф1067mm, according to the grade is divided into two wall thickness 15.9mm and 19.1mm, pipe spacing 30m, the total width of the work with 72m. Among them, 1096 piles and -1097 piles are constructed with a length of 892 meters. The vegetation on the surface of the plot is lush. There is surface water all the year round. The silt layer is thick and the permeability is poor. As a result, it is difficult to enter the construction equipment and the pipe can not be transported. After investigation and repeated on-site investigation, the overall construction program was determined as follows: digging the ditches and draining the dough; This article describes the specific construction of the program. The engineering practice shows that this method has successfully solved the practical difficulties of pipeline construction in the marsh area, and has achieved satisfactory results in construction schedule, quality and cost. It can provide useful reference for pipeline construction in similar areas.