论文部分内容阅读
白龟山水库泄洪闸尾水渠交通桥工程,由河南省水利勘测设计院设计,由河南省水利第一工程局承建,1998年5月1日开工,1999年元月15日竣工。该桥位于白龟山水库泄洪闸下游0+575m处,荷载按汽-20t设计,挂-100t校核,桥长300m,桥两端引桥各20m,桥面行车道宽9m,两侧各设1m宽的人行便道,每孔跨度20m,共15孔。桥基础为混凝土灌注桩,上部为装配式T型梁结构,混凝土路面。主要工程量:混凝
Baiguishan Reservoir Flood Diversion Sluice Drainage Traffic Bridge Project, designed by Henan Province Water Conservancy Survey and Design Institute, was contracted by Henan Water Conservancy Bureau No.1 Project, started on May 1, 1998 and completed on January 15, 1999. The bridge is located at 0 + 575m downstream of the Baiguishan Reservoir sluice gate. The load is designed by steam-20t and checked by -100t. The length of the bridge is 300m. The width of the approach bridge is 20m and the width of the bridge deck is 9m. 1m wide pedestrian crossing, each hole span 20m, a total of 15 holes. The foundation of the bridge is a concrete bored pile, the upper part is an assembled T-beam structure and a concrete pavement. The main volume of engineering: coagulation