“十二五”期间,上海电力股份有限公司在中国电力投资集团公司(现改名为国家电力投资集团公司,注入国家核电资产)海外战略的指导下,制定了“由基本依赖国内资源向依托统筹国内海外两种资源转变”的企业目标,迈出了走向海外的第一步。上海电力的第一个海外项目是为伊拉克华事德地区建设4套330MW燃油电站项目,这个项目是伊拉克政府在战后重建国家电网的一个最大项目,上海电力中标承接了电
During the 12th Five-Year Plan period, under the guidance of overseas strategy of China Power Investment Corporation (now renamed as State Power Investment Corporation and injection of national nuclear assets), Shanghai Electric Power Co., Ltd. formulated the policy of “relying on domestic resources To relying on the co-ordination of both domestic and overseas resources, ”the corporate goals, has taken the first step overseas. The first overseas project of Shanghai Power is to construct 4 sets of 330MW fuel power station project for Huaqian Dehua in Iraq. This project is one of the largest projects for the Iraqi government to rebuild the national grid after the war. Shanghai Electric won the bid to take power