浅谈龙滩水电站坝顶门机吊装难点的克服

来源 :科协论坛(下半月) | 被引量 : 0次 | 上传用户:chenshuae5b
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
龙滩水电站坝顶门机跨距27.5m,额定起重量2×2000KN,与国内水电站同类型坝顶门机相比较属特大型。龙滩坝顶门机的安装难点在于门机上下游支腿距离坝体边缘较近,需要解决支腿吊装时加固问题,同时门机的单节主梁长度及重量较大,需要解决门机主梁的吊装手段问题。安装单位通过跟随坝体浇筑上升进度及时预埋加固挑梁及发挥200吨汽车吊的极限性能,成功解决了以上难题。 Longtan Hydropower Station dam gantry crane span of 27.5m, rated lifting capacity of 2 × 2000KN, compared with the same type of hydropower station dam top door compared to extra large. Longtan dam top door machine installation difficulty is that the upstream and downstream door legs away from the edge of the dam body closer to the need to solve the reinforcement of the leg when lifting the same time, single door gantry length and weight of large, need to solve the main door Beam lifting means problems. The installation unit successfully solved the above problems by following the ascending progress of the pouring of the dam and timely embedding and reinforcing the load beam and exerting the ultimate performance of a 200-ton truck crane.
其他文献
流星余迹通信具有间歇性、信道时变性的特点,大大限制了其网络稳定性和数据传输量,因此,如何提高流星余迹通信的稳定性和数据传输量,是流星余迹通信的关键技术之一。在多基站
由于化工行业对电源的连续性、可靠性的依赖程度极高,面对用户数量如此迅猛的发展,企业规模扩张如此之快,其供电可靠性、用户端安全管理成为我们工作中的重中之重.大用户变配
钢筋工程是钢筋混凝土工程的重要组成部分,要加强钢筋工程施工过程的配料、加工、绑扎、安装等工序质量控制,以确保钢筋工程质量.
木马程序设计最主要的工作是将功能代码实现隐藏,我们可以采用远程线程技术,通过动态链接库方法,借助远程线程将木马作为线程隐藏在其他进程中,从而达到隐藏的目的。 Trojan
注水井的注入压力随着时间、季节的不同变化导致全井配注量的变化,给注水井的管理带来了一定困难,同时也影响了地质开发效果。针对这个问题,介绍三种原理的井口稳流装置,并对
聚类是重要的空间数据挖掘技术,主要用于在隐含的数据中发现有意义的数据分布和数据模式.针对k一~leans算法依赖于聚类中心,聚类个数以及容易陷入局部最优的缺点,提出"蚁群聚
铜冠水运公司从其前身金航轮船公司筹建之始,至今历时整整20年,在这20年里,公司从单船经营发展到目前的集运输、装卸、代理为一体的小型综合企业;从由靠补贴迈入年利润700余
本文介绍了流媒体的网络传输特点和技术,WindowsMedia技术的组成和工作方式,给出了基于流媒体技术的E-learning的设计与应用方案,认为随着网络带宽的增加,适应流式应用的多媒
预应力混凝土是近几十年来发展起来的一门新技术,它是在构件承受外荷载前,预先在构件的受拉区对混凝土施加预压力,这种压力通常称为预应力.提高了构件的抗裂度和刚度.但是在
工业建筑与民用建筑中的防渗漏问题,历来是施工单位和广大用户最为关心的问题.常见渗水部位有:外墙窗四周渗水、卫生间渗水、屋面渗水,空调排水口渗水等,这些问题一直困扰着