论文部分内容阅读
目前,火力发电在总发电容量中还必須占相当大的比重,因此在火电安装中工作量最大、工期最长的鍋爐安装的大跃进,就有特殊重要的意义。最近以来,从事火电建設的职工,在党的領导下,通过双反、双比,政治挂帅,鼓足干勁,鍋爐安装工期已大为縮短。如第45处在洛阳三号爐中,已經创造了57个工作日完成170吨/时炉从第一片鋼架起吊到72小时試运轉完成的記录,而且除全厂保溫以外,只用了三百工人,一般都是两班作业,質量接近优良。但是这样的工期指标还不能滿足今后发展的需要。我們曾就洛阳三号爐,达成跃进的因素进行分析。不能否認,曾經采取了很多先进技术措施,但如果以“十分指标、十二分措施”的要求来衡量,就显得技术措施大大不够。在三号爐中,鍋爐工地的工人們干勁冲天,在相当长的时間內,他們每天工作时間都很长,职工們这种高度的劳动热情,自然是令人感动的,但在今后长期的連續施工中,必須有領导、有計
At present, thermal power generation must also account for a large proportion of the total generation capacity. Therefore, the largest leap forward in the installation of boilers with the largest workload and longest construction period is of special significance. Recently, the workers engaged in thermal power construction, under the leadership of the Party, have adopted dual-opposition and double-ratio, and have led politics with great enthusiasm. The installation period of boilers has been greatly shortened. For example, at No. 45 in Luoyang No. 3 furnace, it has created 57 working days to complete the record of 170 tons/hour furnace lifting from the first steel frame to the completion of 72 hours test run, and in addition to the whole plant insulation, only With three hundred workers, the two classes are generally used and the quality is close to excellent. However, such time limit indicators cannot meet the needs of future development. We analyzed the factors that led to the leap forward in Luoyang No. 3 furnace. It cannot be denied that many advanced technological measures have been taken, but if we measure it with the requirements of “very indicators and twelve measures,” it seems that technical measures are not enough. In the No. 3 furnace, the workers at the boiler site rushed into the sky. For a long time, they worked long hours every day. The high labor enthusiasm of the workers was naturally touched, but In the long-term continuous construction in the future, there must be leadership and