1工程概况平煤七星至姚电公司皮带输煤通道工程区间里程为DK0+874.170~DK2+277.000(全线长1402.83m计934环),其中前100m为始发段。采用盾构法隧道施工,隧道外径为准6000mm,内径为准5400mm,衬砌块宽度1500mm,厚300mm,衬砌管片混凝土设计强度为C50,抗渗强度等级P10;衬砌管片每环六块,由一块封顶块、两块邻接块、两块标准块、一块拱底块拼装而成。平煤七星至姚电公司皮带输煤通道工程项目在盾构施工时要下穿孟宝铁路、南洛高速公路、平顶山市主干道建设路以及湛河等重要建构
1 Project Overview Pingdingshan Qixing to Yao Electric Company Belt Coal Transportation Tunnel Interval mileage DK0 +874.170 ~ DK2 +277,000 (full length 1402.83m meter 934 ring), of which the first 100m for the starting section. The shield tunneling method is adopted. The outer diameter of the tunnel is 6000mm, the inner diameter is 5400mm, the width of the lining block is 1500mm, the thickness is 300mm, the design strength of the lining concrete is C50 and the anti-seepage intensity is P10; It consists of a top block, two adjacent blocks, two standard blocks and an arch bottom block. Pingdingshan Qixing to Yao Electric Company Belt Coal Conveyor Project in the shield construction to go under the Meng Bao railway, Nan Luo Expressway, Pingdingshan Road Construction Road and Zhanhe and other important construction