一九五三年第三季度盘古山钨矿的土建任务是由中南第二工程公司第一工地施工的,八月二十一日才正式开工。其中宿舍工程的青砖柱共64个,高度均为5.8公尺,总计81.1234立方公尺。当时只配备泥工3人,普工3人,徒工2人,而木工则有47人,像这样的工种配合,泥木工种相差悬殊,泥工在完成这样巨大的任务上是有困难的。如用过去的操作方法,比较先进的工效是一工砌3公
The construction of the Pangushan Tungsten Mine in the third quarter of 1953 was started by the construction of the first site of Zhongnan No.2 Engineering Company and was officially started on August 21. Among them, there are 64 brick columns in the dormitory project with a height of 5.8 meters and a total of 81.1234 cubic meters. At that time, there were only 3 masons, 3 general workers, 2 handicraftsmen, and 47 carpentry workers. As with such types of work, there was a great difference between masonry and masonry. It was difficult for masons to accomplish such a huge task. As with the past method of operation, more advanced ergonomics is a puzzle 3 public