平班水电站工程在建设过程中,因地质原因,主体工程施工进度严重滞后,导致大量工程变更和索赔产生。监理机构作为合同管理工作的协调者,在业主授权的范围内,根据索赔事件发生的实际情况,严格按照合同管理程序进行审核,提出意见,使有关经济问题得到较好的解决。介绍了合同内外变更,总价承包项目变更,对因自然灾害、施工干扰引起的经济问题的补偿,赶工奖励,材料价差补偿,设备监造,合同管理,以及索赔与反索赔等方面的情况。
During the construction of Pingban Hydropower Station, due to geological reasons, the progress of construction of the main project lagged seriously, resulting in a large number of engineering changes and claims. As the coordinator of the contract management work, the supervising agency, as the coordinator of the contract management work, conducts an audit in strict accordance with the actual situation of the claim event and in accordance with the contract management procedures and gives opinions so that the relevant economic issues can be better solved. The paper introduces the changes of the contract inside and outside, the change of the general contracting project, the compensation of economic problems caused by natural disasters and construction disturbances, rush reward, materials spread compensation, equipment supervision, contract management, claims and counterclaims.