论文部分内容阅读
BP阿莫科与上海石化股份公司(SPC)投资25亿美元、各持股50%的石化联合项目中,经过研究,乙烯装置能力将由原计划的650kt/a扩增到900kt/a,其他衍生物装置的能力也将作相应调整。该项目仍定于2005年建成投产。项目的建设地点也考虑从金山移至杭州湾北岸约15km的漕泾
BP Amoco and Shanghai Petrochemical Corporation (SPC) have invested 2.5 billion U.S. dollars in a joint petrochemical project with 50% shareholdings. After research, the capacity of ethylene plants will be increased from the originally planned 650kt/a to 900kt/a. Other derivatives The capabilities of the equipment will also be adjusted accordingly. The project is still scheduled to be completed and put into production in 2005. The project site is also considered to be about 15km from Jinshan to the north shore of Hangzhou Bay.