论文部分内容阅读
热电二工段鍋炉的除灰作业,过去从捞灰、装、运灰到卸灰等全部过程都是人工操作,劳动条件差,生产效率低,特別是除灰室的温度高,灰尘大,地区狹窄,操作环境极坏,因此,改变这种落后局面就成了除灰工人的迫切希望。在技术改造运动中,热电二工段职工正党的正确领导下,克服了种种困难,实現了鍋炉除灰机械化联动线,四月上旬已正式投入生产,效果显著。鍋炉除灰机械化联动线如图所示。一、捞灰机結构捞灰机是联动綫中最关鍵的一个机械,它的功用是將排炉落下的灰渣,經水冷却后捞出来装到除灰皮带上,代替捞、装及短距
In the past, the whole process of extracting ash, loading, transporting ash and discharging ash is manual operation, with poor working conditions and low production efficiency, especially when the temperature of the ash removing chamber is high and the dust is large. The area Narrow, the operating environment is very bad, therefore, to change this backward situation has become a desperation ashore workers hope. In the technological transformation campaign, under the correct leadership of the workers and staff of the thermoelectric two section, overcoming all kinds of difficulties and realizing the mechanization linkage of boiler ash removal, the project was put into production in early April and the project has achieved remarkable results. Ash removal mechanized coal boiler line as shown. First, fishing ash machine structure Fishing ash machine linkage line is the most crucial one of the machinery, its function is to discharge the bottom row of ash, after the water cooled out to remove the ash belt, instead of fishing, loading And short distance