1978年6月下旬至7月上旬,在京广线某二级四场双溜单向机械化驼峰的既有编组站上铺设了10组66-11型油压重力式车辆减速器(以下简称减速器)。铺设工程按两期进行,每期5组,各分三次要点施工。减速器的基础系在七十年代初在站场扩建时予埋,路基填料采用底砂及石碴。减速器每组(3节)自重约22吨,实际长度11.995米,位于驼峰线路平面布置上的峰下及第一分支道岔岔后二级制动位式。(见图1)图中①、②、③为第一期工程的铺设顺序,④、⑤、⑥为第二期工程的铺设顺序。
From late June to early July 1978, 10 sets of 66-11 hydraulic gravity type vehicle decelerators (hereinafter referred to as decelerations) were laid on the existing marshalling yards of the second level, Device). Laying the project according to two phases, each of 5 groups, each sub-point construction. The base of reducer was buried at the station expansion in the early seventies. The subgrade filling used sand and ballast. Each reducer (3 knots) weighs about 22 tons and has an actual length of 11.995 meters. It is located on the peak of the hump line layout and the second-stage brake position after the first branch fork. (See Figure 1) ①, ②, ③ for the first phase of the laying of the order, ④, ⑤, ⑥ for the second phase of the laying order.