漫湾水电站位于云南境内澜沧江上,坝高126m,装机容量150万KW,为我国重点水电工程.为了实现当年开工,当年截流的宏伟目标,奋战在我省安康水电站的水电三局抽调了精兵强将,承担了截流的艰巨任务.为了确保截流万无一失,进行了充分的准备工作,现场做了大比尺的模型试验,并在左岸预制了铅丝笼塔.在预计截流落差大、困难度较大的情况下,决定采用双戗交替进占、上戗为主的截流方案.
Manwan Hydropower Station is located in the Lancang River in Yunnan Province, the dam height of 126m, installed capacity of 1.5 million KW, China’s key hydropower projects. In order to achieve the start of the year, then the closure of the grand goal of fighting in the Ankang Hydropower Station in our province, Will undertake the arduous task of closure.In order to ensure that the closure of foolproof, conducted sufficient preparatory work, the site made a large scale model test, and prefabricated lead wire cage tower on the left bank.It is expected that the closure of the flow gap is large, more difficult , The decision to adopt double 戗 alternating takeover, Shang 戗 based closure plan.