近几年来,我国新建连铸机在达产速度上已形成日益加快的势头。如凌钢二钢第一台小方坯连铸机,在投产后第七个月实现月达产,次年就实现年达产。合钢二钢第一台小方坯连铸机投产后第三个月即做到月达产,并实现当年达产。莱钢转炉厂1~#方坯连铸机第14天即作到日达产,创全国连铸机达产速度的新记录;2~#方坯连铸机热试当日、当月即达设计日产、月产水平。邯钢一、二钢新建的矩形坯连铸机,都是当年甚至10个月内达、超设计生产能力。连铸机能够一建成就达到设计生产能
In recent years, the new continuous casting machine in our country has reached an accelerating momentum in reaching the production rate. For example, the first small billet continuous casting machine of Lingang Iron and Steel Co., Ltd reached the monthly output in the seventh month after it was put into production, achieving the annual production in the next year. A steel billet the first billet caster production put into operation the third month after reaching production, and to achieve the year production. Lai Steel BOF plant 1 ~ # billet caster 14 days that is made on a daily basis, creating a new record of the national caster production speed; 2 ~ # billet caster heat test the same day, the month that up to design Nissan, the level of production. Handan Iron and Steel, one or two new rectangular billet continuous casting machine, are the year or even 10 months, super design and production capacity. Caster can be built to achieve the design and production capacity