指出了关键路线法 (CPM)现存在的问题 ,介绍了近年来在国外兴起的项目关键链管理 (CCPM)的基本思想和对 CPM的改进。项目关键链管理的基本思想是根据概率理论和组织行为学理论 ,以 5 0 %的概率估计工期 ,将单个工序的不确定因素统一放在项目缓冲区考虑。将关键链作为项目管理的重点 ,通过项目缓冲区和项目汇入缓冲区的管理来减少延误
Points out the problems existing in the key line method (CPM), and introduces the basic idea of CPM (Project Critical Chain Management) that has arisen abroad in recent years and the improvement of CPM. The basic idea of project key chain management is to estimate the construction period with a probability of 50% according to the theory of probability and the theory of organizational behavior, and to consider the uncertainties of a single operation in the project buffer uniformly. Use key chains as the focus of project management and reduce delays through the management of project buffers and project import buffers