沿海地区存在较多的填海造陆区域,其中不少区域利用粉煤灰回填。粉煤灰颗粒小,渗透性强,易扬尘,充填区临海,地下水水位高,补给速度快,基坑开挖时易渗水和管涌,综合考虑地质情况和经济效益,该工程决定采用高压旋喷桩止水帷幕止水。研究了三管旋喷施工工艺,着重研究如何控制冒浆量和施工中遇到浆液流量、压力等情况异常时的应对措施,以及现场安全用电、控制扬尘等安全环保问题,施工完毕28d后桩体强度检测达标,基坑开挖过程中未出现明显渗漏,说明止水帷幕效果良好。
There are many reclamation areas in coastal areas, of which many areas use fly ash to backfill. Fly ash particles are small, permeability, easy to fly dust, seafill zone, high groundwater level, recharge speed, easy excavation of foundation pit seepage and piping, comprehensive consideration of geological conditions and economic benefits, the project decided to use high-pressure rotary jet Pile stop water curtain stop water. Studied the three-pipe rotary jetting construction technology, focused on how to control the amount of slagging and the slurry flow rate, pressure encountered during construction and other abnormal situations when the response measures, as well as on-site safety of electricity, dust and other safety and environmental issues, construction 28d after completion Pile strength test compliance, pit excavation process did not appear obvious leakage, indicating the effectiveness of water curtain.