1995年5月,在利用世界银行贷款建设的宁波肖镇至梅墟输水钢管工程国际竞争性招标中,我公司以1.3亿元的最低报价中标。1995年10月至1996年底的十五个月。共铺设管道31公里,架设管桥23座,顶管17条789米,累计完成总工程量的80%,为实现20个月全部竣工的奋斗目标奠定了基础。在工程进行中,我公司主要抓了下列工作: 一、科学施工,使国有企业生产潜力得以充分发挥 (一)实行进度目标管理。肖镇至梅墟输水钢管安装工程量大,内容复杂,参建单位近20个。我们把工程总工期作为总体进度目标,同时制定了阶段性目标,三个月为一阶段。其中,前五个阶段的综合目标为确保13.5公里管道于96年底建成通水。每个阶段目标对工程
May 1995, in the use of the World Bank loan construction in Ningbo Xiaozhen to Meilu water pipe project in the international competitive bidding, the company won the bid with a minimum price of 130 million yuan. Fifteen months from October 1995 to the end of 1996. Laying a total of 31 kilometers of pipelines, erecting 23 bridges, pipe jacking 17 789 meters, total completed 80% of the total project, in order to achieve the goal of achieving the full completion of 20 months laid the foundation. In the project, our company mainly grasped the following work: First, the scientific construction, so that the productive potential of state-owned enterprises can give full play to (A) the implementation of the progress of goal management. Shaw Zhen to Mei market water pipe installation of large quantities, the content is complex, nearly 20 participating units. We put the total project duration as the overall progress goal, and at the same time set the phased goal, three months as a stage. Among them, the overall goal of the first five phases is to ensure that the 13.5 km pipeline is completed with water supply by the end of 1996. Each phase of the goal of the project