74年,我们修建了某大型引水工程,其配水厂内,需修建圆形半地下式清水池4座,每座容量为15,000立米。池内径为51.5m,池壁处深5.8m,池中心深8.45m,水深8.3m。池壁由120块预制钢筋混凝土版,拼装而成。(壁板由市政二公司预制场预制)壁板下端插入现场浇制的环形杯口基础内。池底为盆形,整体浇筑。池中有钢筋混凝土柱64根,分
In 74 years, we built a large-scale water diversion project. Within its water distribution plant, four round semi-submerged clear water tanks were built, each with a capacity of 15,000 m3. The inner diameter of the pool is 51.5m, and the depth of the pool wall is 5.8m. The depth of the pool is 8.45m and the water depth is 8.3m. The pool wall is made of 120 prefabricated reinforced concrete panels and assembled. (The siding is prefabricated by the municipal company II prefabricated field) The lower end of the siding is inserted into the cast-in-place annular cup base. The bottom of the pool is pot-shaped and poured in the whole. There are 64 reinforced concrete columns in the pool.