论文部分内容阅读
1总体调试方案分散自律调度集中(CTC)系统的调试,遵循《分散自律调度集中系统技术条件(暂行修订稿)》、《铁路技术管理规程》、《行规》、《站细》等标准。其中车站系统在设备安装完毕,信号联锁、监测系统调试完成,模拟设备未拆除的条件下,首先进行静态调试。调试原则为自下而
1 Overall Commissioning Scheme Commissioning of decentralized autonomous scheduling center (CTC) system follows the standards of “technical conditions of centralized system of decentralized autonomous regulation (tentative revision)”, “railway technical management regulations”, “regulations” and “station details”. Station system in the installation of the equipment is completed, the signal interlocking, monitoring system commissioning is completed, the simulation equipment is not removed under the conditions of the first static debugging. The principle of debugging from the bottom up