摘要:当遇临江道路高水位持续不减时,常规土方开挖,路基施工及支模浇道路砼的施工方法很困难;主要存在问题有:地下水丰富,土方开挖积水多, 易塌方,长期窝工等待,等江水水位降低回落后再施工;道路设计是在设计院提前完成的,路基难以确定合理结构及施工方法,导致道路面层承载力不够;道路采用人工支模浇砼施工进度缓慢。基于以上问题的考虑,为保证工程质量、进度,节约成本,通过查阅以往施工此项目相关技术资料,在分析存在的质量问题的基础上,探索研究一种低于长江水位的临江道路工程的施工技术,并在施工中不断加以改进完善,最终要形成具有一定科技含量的科研成果,为以后类似工程提供借鉴依据。
关键词:临江道路;快速;技术;探析
Abstract: When the high water level of riverside roads continues unabated, conventional earthwork excavation, subgrade construction, and formwork cast road concrete construction methods are very difficult; the main problems are: abundant groundwater, large amounts of water accumulated during earthwork excavation, easy collapse, and long-term Waiting for work, and construction after the river water level drops; road design was completed in advance in the design institute, it is difficult to determine the reasonable structure and construction method of the roadbed, resulting in insufficient bearing capacity of the road surface layer; road construction progress is slow with artificial support form concrete pouring . Based on the consideration of the above issues, in order to ensure the quality, progress and cost saving of the project, by consulting the related technical data of the previous construction of this project, based on the analysis of the existing quality problems, explore and study a kind of riverside road project below the water level of the Yangtze River. Construction technology, and continuous improvement and perfection during construction, will eventually form scientific research results with a certain scientific and technological content, and provide reference for similar projects in the future.
Keywords: riverside road; fast; technology; probing
1引言
武汉新康化工新材料生产基地(一期)道路工程主要由双虎区临江道路、厂前区临江道路组成,为市政工程;长江水位高于该生产基地,挖方后积水多无法施工,因此停工长达数月,一直在寻找解决方法,厂区沿江主线道路长达15000米,该区域建安总量达1亿元;因此,很有必要对该高水位临江道路施工进行创新和研究,以恢复施工并提高施工进度与效益,保证道路施工质量。
2 技术控制难点的解决思路
武汉新康化工新材料生产基地(一期)厂区道路工程,在施工中存在很多技術控制难点问题。通过借鉴以往临江道路施工经验,分析制定了科学合理的施工工序,并对技术难点问题进行了深入研究和创新,采用新的施工工艺和控制技术,在保证进度、质量、安全施工上,起到明显的作用。主要体现在以下几点:
(1)井点降低长江积水层进行道路土方开挖技术,安装可移动排水装置系统,加快排水速度,解决减少挖土方量且不易塌方;并回收利用水资源的井点降水构造施工技术。
(2)现场作试验段道路确定设计构造的施工技术,实施产学研深度融合,现场铺设试验段道路,对道路构造层进行试配[1];试验段道路成型后通过运输车辆对试验段道路进行承载力静载和动载试验,设置沉降观测点进行定期检测,确定最优道路设计构造;解决临江道路高水位施工环境造成路基下沉、路面损坏的问题[2]。
(3)道路面层滑模摊铺及置筋施工技术,安装道路面层滑模摊铺找平收光装置及置筋装置,滑模机的找平收光结构在中横梁上设有可滑动的外构架及连接滑板,滑模摊铺机置筋装置包括支架、千斤顶和活塞式内外套管;降低施工强度,加快道路施工进度。
(4)路缘石机械现浇快速成型施工技术,采用一种路缘石机械现浇快速成型施工的方法,组装路缘石滑模防漏浆装置,路缘石滑模机行走装置带动组装成型模现浇路缘石快速成型,在成型模的下端设有可升降连接的防漏浆板,确保路缘石成型质量。 3井点降低长江积水层进行道路土方开挖
如图1所示,在道路两侧挖降水坑至路基底层以下,道路两侧分段挖设多个降水井坑,井坑内壁设钢板网支撑,井坑点上水管为软管;2根容水主管为移动式,使用滚轮架可推移也可抬动,一端开口式,另一端用塑胶管相连;水集中抽运至水处理池,地下水经过滤、沉淀及消毒;回收的水源要进行水质检测合格后,用于现场砼搅拌站与道路养护,施工道路防尘等,养护管为软管;经收集而多余的地下水翻越堤坝由高压泵抽入至长江;道路基槽开挖后,路基夯实达到要求后才能进行道路基层施工[3]。
4道路面层滑模摊铺及置筋施工
4.1施工工艺
构置组装滑模摊铺机,其采取的技术为摊铺机沿着施工基准线设定的方向和高程前行,混凝土拌和料进入滑模摊铺机的螺旋布料器中,螺旋布料器将混合料均匀地满布于松方控制板前部;机上的成型模板和幅度模板向前滑动,依靠摊铺机自身的重量将混凝土拌和料挤压成型;再利用仓内振动棒组将混凝土振捣密实及排放气泡,夯杆夯实粗集料保证提浆厚度;同时挤压拖抹出混凝土路面的标准断面、光滑的外观和平整度[4];随后的自动搓平板提浆保证路面纵向平整度。滑模摊铺机附带置筋装置,将拉杆置入砼内。
4.2道路滑模摊铺机置筋装置及方法
道路滑模摊铺机置筋装置,可解决现有道路滑模摊铺机置筋不简捷、存在质量风险的问题;其置筋装置构造包括支架、千斤顶和套管,所述千斤顶固定安装于支架上,所述套管包括内套管和外套管,内套管设置于外套管内并可相对伸缩,内套管或外套管一端与所述千斤顶的活塞杆的端部相连。
将支架固定于道路滑模摊铺机尾段的侧面,将需要置入的拉杆装于套管内,内套管和外套管相对延长至道路砼需要置入拉杆的位置,再通过千斤顶将拉杆顶入道路砼中,当顶入至内套管和外套管之间不能相对缩短后停止顶入,或者拉杆的顶入深度达到预定值即停止顶入;拉杆在套管内被顶入,可避免拉杆受力弯曲变形,保证施工质量。
5路缘石机械现浇快速成型施工技术
5.1路缘石机装置要求
1、路缘石机主机安装施工要求
安装路缘石滑模机,其技术是按设计尺寸调整好滑模机成型模,在已用墨线标记的路缘石位置上采用小粒径干式砼进行自动滑模成型路缘石,砼的密度主要靠挤料装置中的螺旋叶片的旋转将混合料挤压在成型模中挤压成型;机械的自动向前移动依靠已成型缘石表面粒料对叶片的反作用力推动整个机械前进。
5.2路缘石滑模防漏浆装置
属于市政工程领域,解决路缘石滑模施工脚边漏浆;路缘石滑模防漏浆装置,包括滑模机身架、组装成型模,承插防漏浆板;所述滑模机身架焊有多根角钢条,以固定组装成型模;所述组装成型模根椐路缘石结构形状组装,组装成型模下部有一承插防漏浆板的挂钩;所述承插防漏浆板一端承插于滑模机身架的竖槽内,可升降;另一端承插于组装成型模下部的挂钩内,可升降;滑模机身架的校正器校正承插防漏浆板的垂直度。组装成型模下部设有承插防漏浆板,有升降功能;承插防漏浆板工作状态是因本身自重与路面紧密结合,可防止路缘石滑模施工脚边砼漏浆,确保路缘石成型的外观质量。
6施工现场道路扬尘防控装置
工地施工道路上车辆通过时尘土飞扬,施工人员及项目办公人员工作环境差,身体健康遭受到很大侵害。
本装置的有益效果是:如图18和图19所示,使用时,将本装置摆放在施工道路两侧,喷雾头和吸尘器朝向施工道路。喷雾头喷出的水雾与扬尘结合,可以把扬尘降下,而除尘器进一步把降下的扬尘抽至路边。本装置能够改善施工现场作业环境,确保现场施工作业人员职业健康安全;也能够避免施工现场扬尘向外弥散。
水源采用回收的地下水,本装置用水量很少,既节省了水资源又避免积水对施工造成的影响。
施工现场道路扬尘防控装置包括防尘单元和供水装置;防尘单元包括底座、喷雾装置和吸尘装置;喷雾装置包括通水立管和喷雾头,通水立管与底座连接,喷雾头与通水立管连通;吸尘装置包括吸尘器和导尘管,吸尘器与通水立管连接并位于喷雾头下方,导尘管与吸尘器连接并延伸至防尘单元底部;供水装置与通水立管连通。底座底部设置有滚轮,喷雾装置包括至少两个喷雾头,吸尘器包括吸尘罩和设置在吸尘罩内吸风风扇;供水装置包括水源、水泵和连接二者的通水软管,水泵的出水口通过水管与通水立管连接;施工现场道路扬尘防控装置包括至少两个防尘单元,各防尘单元设置成一排,相邻防尘单元通过连接杆连接,相邻防尘单元的通水立管通过串联水管连通;供水装置与任一防尘单元的通水立管连通。
图中标记为:防尘单元1、喷雾装置11、通水立管111、喷雾头112、吸尘装置12、吸尘器121、吸尘罩1211、吸风风扇1212、导尘管122、底座13、滚轮131、供水装置2、水源21、水泵22、通水软管23、施工道路3、车辆4、水雾5、扬尘6。
7 结论
通过对武汉新康新材基地高水位临江道路施工方法的总结、提炼、应用和优化,创新了现场作试验段道路确定设计构造的施工技术,运用道路面层滑模摊铺及置筋施工技术新工艺,加快施工进度,确保道路砼施工质量一次合格率98%以上。
参考文献
[1] 蔡志.市政道路软土路基施工技术探析[J].江西建材,2020(09).
[2] 庄志宁.市政工程道路路基施工技术要点探析[J].江西建材,2021(08).
[3] 赵丽娟.公路施工中路基土方开挖技术分析[J].中国公路,2021(05).
[4] 王哲.市政道路路基路面的施工實践思考[J].绿色环保建材,2021(09).
[5] 刘景艳.路面面层施工技术在公路施工中的运用[D].工程技术研究,2020(12).
关键词:临江道路;快速;技术;探析
Abstract: When the high water level of riverside roads continues unabated, conventional earthwork excavation, subgrade construction, and formwork cast road concrete construction methods are very difficult; the main problems are: abundant groundwater, large amounts of water accumulated during earthwork excavation, easy collapse, and long-term Waiting for work, and construction after the river water level drops; road design was completed in advance in the design institute, it is difficult to determine the reasonable structure and construction method of the roadbed, resulting in insufficient bearing capacity of the road surface layer; road construction progress is slow with artificial support form concrete pouring . Based on the consideration of the above issues, in order to ensure the quality, progress and cost saving of the project, by consulting the related technical data of the previous construction of this project, based on the analysis of the existing quality problems, explore and study a kind of riverside road project below the water level of the Yangtze River. Construction technology, and continuous improvement and perfection during construction, will eventually form scientific research results with a certain scientific and technological content, and provide reference for similar projects in the future.
Keywords: riverside road; fast; technology; probing
1引言
武汉新康化工新材料生产基地(一期)道路工程主要由双虎区临江道路、厂前区临江道路组成,为市政工程;长江水位高于该生产基地,挖方后积水多无法施工,因此停工长达数月,一直在寻找解决方法,厂区沿江主线道路长达15000米,该区域建安总量达1亿元;因此,很有必要对该高水位临江道路施工进行创新和研究,以恢复施工并提高施工进度与效益,保证道路施工质量。
2 技术控制难点的解决思路
武汉新康化工新材料生产基地(一期)厂区道路工程,在施工中存在很多技術控制难点问题。通过借鉴以往临江道路施工经验,分析制定了科学合理的施工工序,并对技术难点问题进行了深入研究和创新,采用新的施工工艺和控制技术,在保证进度、质量、安全施工上,起到明显的作用。主要体现在以下几点:
(1)井点降低长江积水层进行道路土方开挖技术,安装可移动排水装置系统,加快排水速度,解决减少挖土方量且不易塌方;并回收利用水资源的井点降水构造施工技术。
(2)现场作试验段道路确定设计构造的施工技术,实施产学研深度融合,现场铺设试验段道路,对道路构造层进行试配[1];试验段道路成型后通过运输车辆对试验段道路进行承载力静载和动载试验,设置沉降观测点进行定期检测,确定最优道路设计构造;解决临江道路高水位施工环境造成路基下沉、路面损坏的问题[2]。
(3)道路面层滑模摊铺及置筋施工技术,安装道路面层滑模摊铺找平收光装置及置筋装置,滑模机的找平收光结构在中横梁上设有可滑动的外构架及连接滑板,滑模摊铺机置筋装置包括支架、千斤顶和活塞式内外套管;降低施工强度,加快道路施工进度。
(4)路缘石机械现浇快速成型施工技术,采用一种路缘石机械现浇快速成型施工的方法,组装路缘石滑模防漏浆装置,路缘石滑模机行走装置带动组装成型模现浇路缘石快速成型,在成型模的下端设有可升降连接的防漏浆板,确保路缘石成型质量。 3井点降低长江积水层进行道路土方开挖
如图1所示,在道路两侧挖降水坑至路基底层以下,道路两侧分段挖设多个降水井坑,井坑内壁设钢板网支撑,井坑点上水管为软管;2根容水主管为移动式,使用滚轮架可推移也可抬动,一端开口式,另一端用塑胶管相连;水集中抽运至水处理池,地下水经过滤、沉淀及消毒;回收的水源要进行水质检测合格后,用于现场砼搅拌站与道路养护,施工道路防尘等,养护管为软管;经收集而多余的地下水翻越堤坝由高压泵抽入至长江;道路基槽开挖后,路基夯实达到要求后才能进行道路基层施工[3]。
4道路面层滑模摊铺及置筋施工
4.1施工工艺
构置组装滑模摊铺机,其采取的技术为摊铺机沿着施工基准线设定的方向和高程前行,混凝土拌和料进入滑模摊铺机的螺旋布料器中,螺旋布料器将混合料均匀地满布于松方控制板前部;机上的成型模板和幅度模板向前滑动,依靠摊铺机自身的重量将混凝土拌和料挤压成型;再利用仓内振动棒组将混凝土振捣密实及排放气泡,夯杆夯实粗集料保证提浆厚度;同时挤压拖抹出混凝土路面的标准断面、光滑的外观和平整度[4];随后的自动搓平板提浆保证路面纵向平整度。滑模摊铺机附带置筋装置,将拉杆置入砼内。
4.2道路滑模摊铺机置筋装置及方法
道路滑模摊铺机置筋装置,可解决现有道路滑模摊铺机置筋不简捷、存在质量风险的问题;其置筋装置构造包括支架、千斤顶和套管,所述千斤顶固定安装于支架上,所述套管包括内套管和外套管,内套管设置于外套管内并可相对伸缩,内套管或外套管一端与所述千斤顶的活塞杆的端部相连。
将支架固定于道路滑模摊铺机尾段的侧面,将需要置入的拉杆装于套管内,内套管和外套管相对延长至道路砼需要置入拉杆的位置,再通过千斤顶将拉杆顶入道路砼中,当顶入至内套管和外套管之间不能相对缩短后停止顶入,或者拉杆的顶入深度达到预定值即停止顶入;拉杆在套管内被顶入,可避免拉杆受力弯曲变形,保证施工质量。
5路缘石机械现浇快速成型施工技术
5.1路缘石机装置要求
1、路缘石机主机安装施工要求
安装路缘石滑模机,其技术是按设计尺寸调整好滑模机成型模,在已用墨线标记的路缘石位置上采用小粒径干式砼进行自动滑模成型路缘石,砼的密度主要靠挤料装置中的螺旋叶片的旋转将混合料挤压在成型模中挤压成型;机械的自动向前移动依靠已成型缘石表面粒料对叶片的反作用力推动整个机械前进。
5.2路缘石滑模防漏浆装置
属于市政工程领域,解决路缘石滑模施工脚边漏浆;路缘石滑模防漏浆装置,包括滑模机身架、组装成型模,承插防漏浆板;所述滑模机身架焊有多根角钢条,以固定组装成型模;所述组装成型模根椐路缘石结构形状组装,组装成型模下部有一承插防漏浆板的挂钩;所述承插防漏浆板一端承插于滑模机身架的竖槽内,可升降;另一端承插于组装成型模下部的挂钩内,可升降;滑模机身架的校正器校正承插防漏浆板的垂直度。组装成型模下部设有承插防漏浆板,有升降功能;承插防漏浆板工作状态是因本身自重与路面紧密结合,可防止路缘石滑模施工脚边砼漏浆,确保路缘石成型的外观质量。
6施工现场道路扬尘防控装置
工地施工道路上车辆通过时尘土飞扬,施工人员及项目办公人员工作环境差,身体健康遭受到很大侵害。
本装置的有益效果是:如图18和图19所示,使用时,将本装置摆放在施工道路两侧,喷雾头和吸尘器朝向施工道路。喷雾头喷出的水雾与扬尘结合,可以把扬尘降下,而除尘器进一步把降下的扬尘抽至路边。本装置能够改善施工现场作业环境,确保现场施工作业人员职业健康安全;也能够避免施工现场扬尘向外弥散。
水源采用回收的地下水,本装置用水量很少,既节省了水资源又避免积水对施工造成的影响。
施工现场道路扬尘防控装置包括防尘单元和供水装置;防尘单元包括底座、喷雾装置和吸尘装置;喷雾装置包括通水立管和喷雾头,通水立管与底座连接,喷雾头与通水立管连通;吸尘装置包括吸尘器和导尘管,吸尘器与通水立管连接并位于喷雾头下方,导尘管与吸尘器连接并延伸至防尘单元底部;供水装置与通水立管连通。底座底部设置有滚轮,喷雾装置包括至少两个喷雾头,吸尘器包括吸尘罩和设置在吸尘罩内吸风风扇;供水装置包括水源、水泵和连接二者的通水软管,水泵的出水口通过水管与通水立管连接;施工现场道路扬尘防控装置包括至少两个防尘单元,各防尘单元设置成一排,相邻防尘单元通过连接杆连接,相邻防尘单元的通水立管通过串联水管连通;供水装置与任一防尘单元的通水立管连通。
图中标记为:防尘单元1、喷雾装置11、通水立管111、喷雾头112、吸尘装置12、吸尘器121、吸尘罩1211、吸风风扇1212、导尘管122、底座13、滚轮131、供水装置2、水源21、水泵22、通水软管23、施工道路3、车辆4、水雾5、扬尘6。
7 结论
通过对武汉新康新材基地高水位临江道路施工方法的总结、提炼、应用和优化,创新了现场作试验段道路确定设计构造的施工技术,运用道路面层滑模摊铺及置筋施工技术新工艺,加快施工进度,确保道路砼施工质量一次合格率98%以上。
参考文献
[1] 蔡志.市政道路软土路基施工技术探析[J].江西建材,2020(09).
[2] 庄志宁.市政工程道路路基施工技术要点探析[J].江西建材,2021(08).
[3] 赵丽娟.公路施工中路基土方开挖技术分析[J].中国公路,2021(05).
[4] 王哲.市政道路路基路面的施工實践思考[J].绿色环保建材,2021(09).
[5] 刘景艳.路面面层施工技术在公路施工中的运用[D].工程技术研究,2020(12).