今年第二季,北京电管局基建五处担负了一条长达百里的超高压线路的施工任务。这条线路有一半要经过悬崖峭壁、峰峦重迭的山区,沿线35%的地带为岩石,15%的地带有水。整个工程工作量大,劳动力不足,材料供应也很紧张,水泥、木材不足,而工期要求紧迫。在这种情况下,怎么办?这个处的领导上及时提出了“冲天干劲突难关,智取超高压线”的口号。这一振奋人心的号召发出后,极大的鼓舞了职工的干劲,一个轰轰烈烈的技术革命运动就开展起来了。由于苦干与巧干相结合,大力推行新技术,不到一个月就在解决山区运输,开挖土石方、大量节约水泥、木材等问题上收到了显著成
In the second quarter of this year, the 5th Infrastructure Department of Beijing Electric Power Bureau took on the task of constructing an ultra-high-pressure line up to 100 miles. Half of this route will pass through cliffs and mountains with overlapping peaks. Rocks will be found in 35% of the area and water will be found in 15% of the area. The entire project has a large workload, lack of labor, supply of materials is also very tight, lack of cement and wood, and the construction period is urgent. In this case, what should I do? The leader of this department promptly put forward the slogan of “Chongtianjinjin sudden difficulties, wisdom to take the UHV line”. After this inspiring call was issued, it greatly encouraged the staff’s energy and a vigorous technological revolution began. Thanks to the combination of hard work and Qiaogan, the new technology was vigorously promoted. In less than a month, significant achievements were received in the settlement of mountain transportation, excavation of earth and stone, substantial savings of cement, timber and other issues.