承担大连第二发电厂扩建工程安装任务的水利电力部沈阳电力建设局十五工程处,放出快速安装发电设备“卫星’,创造了只用14天零20小时就安装一台供热式高温高压25,000瓩汽轮发电机的全国最高纪录。接着他们又用不到7天时间使这个机组开始发电。这台大型发电设备的安装工作是从9月17日开始的,国家原计划于明年第二季度末发电,经过一再跃进后要求于10月底发电。在安装当中,干部和群众人人思想插红旗,自己编
The 15th Engineering Bureau of the Shenyang Electric Power Construction Bureau of the Ministry of Water Resources and Electric Power, which is responsible for the installation of the expansion project of the Dalian No. 2 Power Plant, released the rapid installation of the power generation equipment ”satellite," creating a heating-type high temperature in only 14 days and 20 hours. The highest national record for high-pressure 25,000-inch turbo-generators, and then they took less than seven days to make this unit start generating electricity. The installation of this large-scale power plant started from September 17 and the country originally planned to be the next year. At the end of the second quarter, power generation, after repeated leaps, was required to generate electricity at the end of October. During the installation, the cadres and the masses of people thought to insert red flags and edited themselves.