随着2013年5月15日最后一批水泥固化桶顺利运抵处置场现场,中国原子能科学研究院水泥固化体Ⅰ期外运与处置任务圆满完成。本项工作自2011年10月开始,历时19个月,回取与转运9个批次,共计3 300桶水泥固化体,前期大量的准备工作和过程中不断的改进工作保证了整个外运工作的安全顺利完成。2013年度是本项目任务最重的一年,3—5月共计完成了五批次的外运任务,共计近1 500桶。中国原子能科学研究院负责现场回取与转运工作,此项工作的运行时间规律属短期(2~5 d)24 h
With the final batch of cement curing barrels successfully delivered to the disposal site on May 15, 2013, the phase I outsourcing and disposal tasks of the cement solidified bodies of China Institute of Atomic Energy completed satisfactorily. This work began in October 2011 and lasted 19 months. Nine batches of withdrawals and transshipment batches were made, amounting to 3 300 barrels of cement solidified bodies. A large amount of preparatory work and continuous improvement work in the previous period ensured that the entire outbound work The safety is completed successfully. The year 2013 was the heaviest year for this project. From March to May, a total of five batches of foreign missions were completed, totaling nearly 1,500 barrels. China Institute of Atomic Energy is responsible for on-site retrieval and transshipment work, the law of the operation time is a short-term (2 ~ 5 d) 24 h