混凝土斜拉桥主梁常采用前支点挂篮现浇施工,施工中容易出现主梁混凝土上下游不同步浇筑,为分析混凝土浇筑上下游不同步对施工控制的影响及处理措施,该文以贵州六冲河特大桥(主跨438m预应力混凝土斜拉桥)为工程背景,建立主桥和挂篮结构空间杆系模型,计算分析施工过程中输送混凝土管道难以及时移动和拆除再拼装导致浇筑混凝土时上下游所浇混凝土方量不同步对主梁标高、索力和挂篮受力的影响,并提出以控制拉索延伸量为目标的自适应无应力控制法,解决浇筑过程中上下游不同步对施工控制的影响。
The main beam of the concrete cable-stayed bridge often adopts the former fulcrum hanging basket cast-in-place construction. The construction of the main girder is prone to occur with the unsynchronized pouring of the upstream and downstream of the concrete girder. In order to analyze the influence of unsynchronized upstream and downstream of the concrete pouring on the construction control and the treatment measures, As the background of the project, the model of the space bar of the main bridge and hanging basket structure was established. The transportation and transportation of concrete pipes in the process of construction were difficult to move in time and the reassembly led to the pouring of concrete When the amount of concrete poured in the upper and lower reaches is not synchronized, the effect of the standard height of the main beam, the cable force and the load on the cradle is affected. An adaptive stress-free control method is proposed to control the extension of the cable. The impact of synchronization on construction control.