(一) 在流域规划阶段及初设准备阶段,我们采用了苏联先进经验:“用折算砼土方来计算水工建筑物的造价”。从而比较简捷地进行计算工作,并且大大地节省了工作量,由于造价指标在统一的基础上,根据枢纽施工条件所求出,因此能保证成果的准确性。现将砼折算规程的基本原则与内容介绍如下: (1)采用折砼方法,确定主要建筑物中主要建筑安装工程项目的造价; (2)确定建筑安装工程的造价,将主要建筑安装工程的土建项目换算成砼,再乘1公方折砼的价格; (3)利用折算系数,将建筑安装工程的土建项目换算砼,其折算系数等于各类工程的单位价格
(A) At the stage of river basin planning and initial preparation, we have adopted the advanced experience of the Soviet Union: “Calculating the cost of hydraulic structures by using concrete instead of concrete.” Therefore, the calculation work is relatively simple, and the workload is greatly saved. Since the cost indexes are obtained on the basis of the unified construction conditions according to the pivoting construction conditions, the accuracy of the results can be guaranteed. The concrete principles and contents of concrete conversion procedures are as follows: (1) The method of folding concrete is adopted to determine the cost of major construction installation projects in major buildings; (2) The cost of construction and installation works is determined, and the cost of major construction and installation works Civil engineering projects converted into concrete, and then by 1 square folded concrete prices; (3) the use of conversion factor, the civil engineering construction and installation projects converted concrete, the conversion coefficient is equal to the unit price of various projects