五强溪水电站工程最后一台机组已于1996年12月投产发电。回顾总结建设施工过程中施工导流三期改二期,提高坝基开挖高程,厂房左导墙与5号机组混凝土分开施工,大坝混凝土通仓薄层浇筑,选定坝顶门机安装场地,坝顶门机预应力梁改钢梁,人工砂石系统技术攻关及增容改造等重大技术问题的科学论断、正确决策、团结实干,既赢得了工期,也减少了工程量,从而保证了全部工程按期投运总目标的如期实现。
The last unit of the Wuqiangxi Hydropower Project was put into production in December 1996. Reviewing and summarizing the three phases of the construction diversion during the construction and construction, improving the excavation height of the dam foundation, separate the construction of the left guide wall of the plant and the concrete of the No. 5 unit, pouring the thin concrete layer of the concrete dam, and selecting the installation site for the dam door machine. The scientific conclusion, correct decision-making, solidarity, and solid work of major technical issues such as the change of pre-stressed beams from the crest-gate door to the steel girders, artificial gravel systems, and capacity expansion and transformation have won the construction period and reduced the amount of work, thus ensuring that all projects are on schedule. The overall goal of the transport is achieved on schedule.