论文部分内容阅读
(一)电站概况龙滩水电站在红水河综合利用规划的10个梯级电站中是关键骨干工程,库容最大,达272亿m~3;装机容量最大,达540万kW。龙滩水电站除本站发电效益外,并可增加下游梯级电站的发电效益;还有防洪、通航等综合利用效益,故俗称“龙头”水电站。 (二)立项前的经历 1981年10月,国家能源委员会和国家计划委员会共同组织召开红水河综合利用规划审查会议。审查报
(I) Overview of Power Plant Longtan Hydropower Station is the key backbone project of 10 cascade hydropower stations in the comprehensive utilization planning of Hongshui River, with the largest storage capacity of 27.2 billion m 3 and the largest installed capacity of 5.4 million kW. Longtan Hydropower Station in addition to generating efficiency of this station, and can increase the downstream cascade hydropower generating benefits; as well as flood control, navigation and other comprehensive utilization benefits, it is commonly known as “leading” hydropower station. (II) Pre-project experience In October 1981, the National Energy Commission and the State Planning Commission jointly organized and held a review meeting on the comprehensive utilization of the Red River. Review Newspaper