阜新发电厂的全体职工,发愤图强.奋战不懈,以三十四天装好一台大型的汽轮发电机,比以前安装的一台同类型汽机,整整快了一倍,十分顺利地一次起动成功,震动最大的轴瓦也未超过三道(三丝米)。与此同时,又提前以六十三天组合、吊装了两台大型锅炉的大件.为冬季封闭厂房创造了.条件;起吊第一台锅炉的大件只用了二百三十八小时,吊装后到水压试验只用了二十六天,起吊第二台炉的大件又缩短到一百八十
The entire staff of the Fuxin Power Plant has become very aggressive and has worked tirelessly to install a large turbogenerator in 34 days. It is twice as fast as a previously installed turbine of the same type, and it is very smooth once. Successfully started, the maximum vibration of the bearing did not exceed three (three meters). At the same time, the two large-scale boilers were erected in a combined assembly of 63 days in advance. The conditions for the closure of the plant were created in the winter. The large pieces of the first boiler had only been used for 238 hours. It took only 26 days after the lifting to the hydrostatic test, and the large piece of the second furnace was shortened to 180