摘要:现在住宅建筑设计多种多样,外观异形特别,由且是作为室内采光的阳台,有凸有凹,直接影响到外架防护的措施编制。楼层休息平台的标高,是否与层高一致都会导致外挑架的底面平整和结构的受力不均,直接影响建筑工程的质量的作业人员的安全。因此,本文通过对两种常见的结构外形进行比选优化,达到了成本节约,安装便捷的目的。对类似工程的挑架设计、施工具有指导意义。
关键词:悬挑脚手架;楼梯间;转角;阳台;挑梁
中图分类号:TU226文献标识码: A
Optimization of hanging scaffold building F7# house two
Xin Kang home
Jiao Bo , Li Zhu Ping
(Shanxi Hong Xia third construction projects Co. Ltd.yangquan 045000,China)
Abstract: Now many residential building design diversity, special-shaped special appearance, and is as indoor lighting balcony, a convex and concave, directly affects the external frame protection measures for. The rest of the platform floor elevation, and whether the agreement will lead to high cantilever rack bottom is flat and the structure of the uneven stress, directly affect the quality of construction workers safety. Therefore, this paper optimize the comparison and selection of two kinds of structure shape, to save cost, convenient installation purpose. Has the instruction significance to the scaffold design, the construction of similar engineering.
Keywords:Cantilever scaffold;Stair case;Angle;The balcony;Cantilever beam
1.概況
馨康家园二期F7#住宅楼工程位于阳泉市王岩沟,地下3层,地上18层,负一层为储藏室,负二层为管道层,负三层为人防层。总建筑面积12187.01m2,建筑总高为57.5m。
考虑到节约成本,本工程没有选择成品爬架,而选择传统的悬挑脚手架作为安全防护。悬挑脚手架用于2层以上住宅部分的外墙围护,在2层底板面上布置悬挑架,挑架每6层一挑,在二次结构外墙砌筑完、阳台样板浇筑完后拆除。为了保证周转,需要12层外架材料、两层的挑架工字钢、卸荷钢丝绳、三层的预埋环。
2.悬挑架平面布置图
悬挑架方案一
悬挑架方案二
3. 优化一:楼梯间处休息平台设挑梁
方案一:在楼梯间两侧楼层梁设预埋件各两个,增加两根16号工字钢做支撑,上面焊接锚环。优点是可以保证和同层的挑梁水平,外观整齐美观。
方案二:在楼梯间休息平台处设挑梁。本工程休息平台宽度为2.4m,长1.5m。按规范要求锚固长度/悬挑长度=1.25,休息平台处锚固长度不够,所以必须减少该部位的荷载,因此该处挑梁的横距缩小为1.2m(其它间距均为1.5m)。优点是节约材料,但是与同层的挑梁有错台。
4. 优化二:大角处设置45。斜挑梁
方案一:在外墙大角处设置纵横交错的悬挑梁,悬挑端纵向增加悬挑工字钢,保证大角处的立管支撑。预埋环需要加长,浪费了材料,增加了悬挑端荷载,且锚固端有错台不美观。
图4.1 方案一:大角处纵横交错悬挑梁 图4.2 方案二:大角处设置45.悬挑梁
方案二:在外墙大角处先设置45。斜挑梁,挑梁长4.5m。其余靠近大角处挑梁与之相碰时,保证斜挑梁完整,切割别的挑梁,节点处增加连接钢板,焊缝为6mm角焊缝。预埋环、工字钢减少了,节约了材料,且锚固端平整美观。
5.优化三:凹阳台处增加支撑钢梁
方案一:在凹阳台处加长挑梁,按规范要求采用7m长16号工字钢可以承受外架的荷载,但是7m长的挑梁,重约145kg,工人搬运不方便,二次周转使用更不安全。悬挑长度2.7m,挑梁挠度过大,存在安全隐患。
图5.1 方案一:凹阳台处加长挑梁图5.2 方案二:凹阳台处增加支撑钢梁
方案二:在凹阳台处增加支撑钢梁,钢梁长4.5m,重90kg。增加钢梁后,挑梁的支撑点转移,和外墙一致,承受相同的荷载的情况下,该处的挑梁长缩短到4.5m。减小工人搬运难度,提高了周转效率,保证了挑架立面的平整度。
图5.3 挑架立面平整 图5.4 凹阳台处增加支撑钢梁
6. 经济效益分析
经济效益分析
结 语:
经过上述三个方面的优化,周转材料用量减少,占用周期缩短,降低了工程成本;优化后的方案满足规范和设计的要求, 为主体施工创造了条件,同时,对工程的成本控制、质量控制、进度控制、安全管理起到了积极的作用。
参考文献:
[1] 《建筑结构荷载规范》GB50009-2012 中华人民共和国住房和城乡建设部 2012年12月1日
[2] 《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011 中华人民共和国住房和城乡建设部 2011年12月1日
[3] 《建筑施工安全检查标准》JGJ59-2011 中华人民共和国住房和城乡建设部 2012年7月1日
[4]江正荣. 《建筑施工计算手册》(第二版)2007年7月
[5]杨嗣信,侯君伟. 《高层建筑施工手册》(第二版)2001年6月
关键词:悬挑脚手架;楼梯间;转角;阳台;挑梁
中图分类号:TU226文献标识码: A
Optimization of hanging scaffold building F7# house two
Xin Kang home
Jiao Bo , Li Zhu Ping
(Shanxi Hong Xia third construction projects Co. Ltd.yangquan 045000,China)
Abstract: Now many residential building design diversity, special-shaped special appearance, and is as indoor lighting balcony, a convex and concave, directly affects the external frame protection measures for. The rest of the platform floor elevation, and whether the agreement will lead to high cantilever rack bottom is flat and the structure of the uneven stress, directly affect the quality of construction workers safety. Therefore, this paper optimize the comparison and selection of two kinds of structure shape, to save cost, convenient installation purpose. Has the instruction significance to the scaffold design, the construction of similar engineering.
Keywords:Cantilever scaffold;Stair case;Angle;The balcony;Cantilever beam
1.概況
馨康家园二期F7#住宅楼工程位于阳泉市王岩沟,地下3层,地上18层,负一层为储藏室,负二层为管道层,负三层为人防层。总建筑面积12187.01m2,建筑总高为57.5m。
考虑到节约成本,本工程没有选择成品爬架,而选择传统的悬挑脚手架作为安全防护。悬挑脚手架用于2层以上住宅部分的外墙围护,在2层底板面上布置悬挑架,挑架每6层一挑,在二次结构外墙砌筑完、阳台样板浇筑完后拆除。为了保证周转,需要12层外架材料、两层的挑架工字钢、卸荷钢丝绳、三层的预埋环。
2.悬挑架平面布置图
悬挑架方案一
悬挑架方案二
3. 优化一:楼梯间处休息平台设挑梁
方案一:在楼梯间两侧楼层梁设预埋件各两个,增加两根16号工字钢做支撑,上面焊接锚环。优点是可以保证和同层的挑梁水平,外观整齐美观。
方案二:在楼梯间休息平台处设挑梁。本工程休息平台宽度为2.4m,长1.5m。按规范要求锚固长度/悬挑长度=1.25,休息平台处锚固长度不够,所以必须减少该部位的荷载,因此该处挑梁的横距缩小为1.2m(其它间距均为1.5m)。优点是节约材料,但是与同层的挑梁有错台。
4. 优化二:大角处设置45。斜挑梁
方案一:在外墙大角处设置纵横交错的悬挑梁,悬挑端纵向增加悬挑工字钢,保证大角处的立管支撑。预埋环需要加长,浪费了材料,增加了悬挑端荷载,且锚固端有错台不美观。
图4.1 方案一:大角处纵横交错悬挑梁 图4.2 方案二:大角处设置45.悬挑梁
方案二:在外墙大角处先设置45。斜挑梁,挑梁长4.5m。其余靠近大角处挑梁与之相碰时,保证斜挑梁完整,切割别的挑梁,节点处增加连接钢板,焊缝为6mm角焊缝。预埋环、工字钢减少了,节约了材料,且锚固端平整美观。
5.优化三:凹阳台处增加支撑钢梁
方案一:在凹阳台处加长挑梁,按规范要求采用7m长16号工字钢可以承受外架的荷载,但是7m长的挑梁,重约145kg,工人搬运不方便,二次周转使用更不安全。悬挑长度2.7m,挑梁挠度过大,存在安全隐患。
图5.1 方案一:凹阳台处加长挑梁图5.2 方案二:凹阳台处增加支撑钢梁
方案二:在凹阳台处增加支撑钢梁,钢梁长4.5m,重90kg。增加钢梁后,挑梁的支撑点转移,和外墙一致,承受相同的荷载的情况下,该处的挑梁长缩短到4.5m。减小工人搬运难度,提高了周转效率,保证了挑架立面的平整度。
图5.3 挑架立面平整 图5.4 凹阳台处增加支撑钢梁
6. 经济效益分析
经济效益分析
结 语:
经过上述三个方面的优化,周转材料用量减少,占用周期缩短,降低了工程成本;优化后的方案满足规范和设计的要求, 为主体施工创造了条件,同时,对工程的成本控制、质量控制、进度控制、安全管理起到了积极的作用。
参考文献:
[1] 《建筑结构荷载规范》GB50009-2012 中华人民共和国住房和城乡建设部 2012年12月1日
[2] 《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011 中华人民共和国住房和城乡建设部 2011年12月1日
[3] 《建筑施工安全检查标准》JGJ59-2011 中华人民共和国住房和城乡建设部 2012年7月1日
[4]江正荣. 《建筑施工计算手册》(第二版)2007年7月
[5]杨嗣信,侯君伟. 《高层建筑施工手册》(第二版)2001年6月