论文部分内容阅读
铁道部建厂局二处在承建某招待所增建工程中,实行全优定包合同制与奖金包干办法,取得较好的经济效益。该楼座落在济南市经二纬三路之间的升平街口内,地处市区中心闹市,街道又窄,沿街行人川流不息,要将原来三层屋面揭盖,增建两层,建筑面积13 27平方米,投资21.5万元,工期4个月。由于组织40多人的包干小分队,对瓦工、混凝土工等实行包干合同和奖金包干,较好地完成了施工任务,实现了多劳多得。具体做法有以下几点:一、实行奖金包干的条件:质量达到国家验收标准;工期按所订协议
The Construction Bureau of the Ministry of Railways established a method of contracting and awarding bonuses in the construction of a guest house in the construction of an additional building project to achieve better economic benefits. The building is located in the street of Shengping Street between Jingwei Street and Erwei 3rd Road in Jinan City. It is located in the downtown area of downtown and the streets are narrow. The pedestrians on the street are constantly flowing. The original three-storey roof is uncovered and the two floors are newly built. With an area of 13 27 square meters and an investment of 215,000 yuan, the construction period is 4 months. Due to the organization of more than 40 people’s lump sum teams, the implementation of lump sum contracts and bonuses for bricklayers, concrete workers, etc., completed the construction tasks better, and achieved more work and more work. The specific methods include the following points: 1. The conditions for the implementation of the bonus contract: the quality meets the national acceptance criteria;