为了确保金河水电站大坝右岸砂石料场生产系统及拌和系统的早日建成,满足导流洞混凝土衬砌的骨料供应。经多方衡量决定,金河大桥采取冬季施工方案。因当地无冬季施工经验资料借鉴,且冬季气候条件较差,水平运输混凝土入模温度难以保证,常规的混凝土保温措施无法达到规范要求的温度。故根据西藏昌都地区的特殊地理环境及气候特点,因地制宜地制定了相应的冬季施工准则及管理办法,有效地保证了大桥工程的质量和进度。
In order to ensure the early completion of the production system and mixing system of the right bank of the Jinhe Hydropower Station dam, the supply of aggregate for the diversion tunnel concrete lining is satisfied. After a number of measurement decisions, the Golden River Bridge to take winter construction program. Because there is no local experience in winter construction and learn from the information, and poor winter weather conditions, horizontal transport of concrete into the mold temperature is difficult to guarantee, conventional concrete insulation measures can not meet the requirements of the standard temperature. Therefore, according to the special geographical environment and climate characteristics of the Qamdo area in Tibet, corresponding winter construction guidelines and management measures are formulated according to local conditions, which effectively ensure the quality and progress of the bridge project.