我公司在施工中改变了传统的施工顺序,将空心板安装工序提前到浇筑楼面结构混凝土之前进行。具体做法如下。1.每个流水段的墙体砌完以后,钢筋工与木工先完成与搁置空心板有联系的工作,所不同的是,木工立模的穿墙楞,要用木方或毛竹支顶在下一层楼板或基土上。基土应该夯实,并且垫上木板,以防止搁置空心板时倾覆。具体施工做法见图1、2、3。应该注意的是,支顶必须牢固。模内上部用长24厘米的小木方或短钢筋
Our company changed the traditional construction sequence during construction and advanced the installation of hollow slabs prior to pouring concrete for the floor structure. The specific approach is as follows. 1. After the wall of each water section is finished, the steelworker and the woodworker first complete the work related to the shelving of the hollow board. The difference is that the woodworker’s model must pass through the wall and use wood or bamboo under the roof. One floor or base soil. The foundation soil should be compacted and planked to prevent overturning when the hollow slab is rested. Specific construction practices are shown in Figures 1, 2, and 3. It should be noted that the top must be strong. In the upper part of the mold, a small wooden or short steel bar with a length of 24 cm is used