泥沙的淤积,是水库、电站非常关心的问题。根据实测泥沙资料,按沙量平衡原理计算麻石库区的泥沙淤积情况,现介绍如下。麻石电站位于都柳江和浔江的汇合口下游26.8公里处的融江河段上(见图1),以发电为主。总库容2.7亿米~3,有效库容0.6亿米~3,库区集水面积19940平方公里,水库上下游均设有水文站。一、水文站分布情况 (一)入库站: 1.涌尾站位于都柳江下游,集水面
Silt sedimentation is a reservoir, power plants are very concerned about the issue. According to the measured sediment data, according to the principle of sand balance calculation of the reservoir area of ?? muddy sediment, are as follows. The Mashi power station is located on the Rongjiang reach 26.8 kilometers downstream of the confluence of the Duliujiang River and the Hanjiang River (see Figure 1), mainly for power generation. The total storage capacity of 270 million meters to 3, the effective storage capacity of 060 million meters ~ 3, the reservoir area of 19940 square kilometers of water catchment, upstream and downstream of the reservoir are equipped with hydrological stations. First, the distribution of hydrological stations (A) storage station: 1 Chung Wei station is located in the lower reaches of Liujiang, catchment