论文部分内容阅读
2008年6月30日,中国第一条从陆路引进境外天然气的跨国能源通道——中亚天然气管道,在乌兹别克斯坦南部的历史名城布哈拉动工建设。中亚天然气管道全长1 801 km,采用大口径、高钢级管材,按双线并行方式敷设,西起土乌边境,穿越乌兹别克斯坦中部和哈萨克斯坦南部地区,在中国新疆霍尔果斯入境。由中石油分别与乌兹别克斯坦油气公司、哈萨克斯坦油气公司成立天然气管道合资公司,共同建设。预计2009年底实现单线通气,2010年实现
On June 30, 2008, China started its construction of the Central Asian natural gas pipeline, a trans-national energy corridor for the import of overseas natural gas by land, in Bukhara, a historic city in southern Uzbekistan. The total length of the Central Asian natural gas pipeline is 1,801 km. It is constructed of large-diameter and high-grade steel pipes and laid in a two-lane parallel manner. From the border of Tuu and Uruguay, it passes through central Uzbekistan and southern Kazakhstan and enters China at Horgos, Xinjiang . CNPC respectively set up a natural gas pipeline joint venture with Uzbekistan oil and gas companies and Kazakhstan Oil and Gas Company to jointly build. Single-line ventilation is expected to be achieved by the end of 2009, achieved in 2010