我队承担一组高压电网铁塔基础桩的施工任务,桩径1米,桩深10.5米;下入钢筋笼长10米,笼φ840毫米,地处江边纯砂质地层,交通不便,采用了冲抓锥冲抓成孔,汽车吊下笼,灌注混凝土成柱。在施工过程中,始终掌握二条原则:一是保证泥浆粘度和孔内注满泥浆,以实现平衡压力;二是冲抓锥的平稳操作,以免碰刮孔壁。从而保证了工程的顺利实施。给我们提供了成功的经验。冲抓锥用来施工第四纪大口径水井和基桩孔,或作为基岩端承桩前期工程配套工艺,由于其可拆性强。工程简单,对交通条件不好,施工场地狭窄都能适应,是值得重视的一项钻探工艺。
Our team is responsible for the construction of a group of high-voltage grid tower foundation piles, with a diameter of 1 meter and a pile depth of 10.5 meters. The steel cage is 10 meters long and has a cage diameter of 840 millimeters. It is located on the riverside in a pure sand formation and is inconvenient for traffic. Chong grasping cone punching hole, the car hanging cage, pouring concrete into columns. In the construction process, always grasp the two principles: First, to ensure that the mud viscosity and hole filled with mud in order to achieve equilibrium pressure; second is the smooth operation of the punch grab cone, so as not to scratch the hole wall. This ensures the smooth implementation of the project. Give us a successful experience. The rush cone is used to construct the Quaternary large-diameter wells and foundation pile holes, or as a supporting engineering for bedrock piles in the early stage of the pile, due to its strong detachability. The project is simple, it is not suitable for the traffic conditions, and the construction site can be adapted to the narrowness. It is a drilling process worthy of attention.