论文部分内容阅读
长期以来,沈阳市话通信一直处于紧张状态。去年初全市电话待装户多达14,727户。为了改变这种被动局面,1983年全局放号3,112户,提前59天完成了年放号3,000户的计划,比上年增长52%,创造了我局历年放号的最高记录。主要做法是: 一、改革管理体制,加快基建、放号速度。我们首先改革了基建管理体制,建立由生产副局长直接领导的基建调度室,充实了管理和技术骨干,加强了计划的前期工作和设计、施工、验收各个环节的管理,注意提高质量,机线配套,尽快发挥投资效益。1981年以来,全局共装机13,300门。其中1983年开通5,400门。三年共建电缆管道74.2公里,新建主干
For a long time, Shenyang local telephone communication has been in a state of tension. At the beginning of last year, the city’s telephone households up to 14,727 households. In order to change this passive situation, in 1983, the overall number was 3,112, 59 days ahead of schedule was completed for 3,000 households, an increase of 52% over the previous year, creating the highest record in the calendar year. The main approach is: First, reform the management system, speed up infrastructure, release speed. We first reform the infrastructure management system and establish an infrastructure control room directly led by the deputy director of production. We have enriched the management and technical backbone, strengthened the preliminary work of the plan and the management of all aspects of design, construction and acceptance, and paid attention to improving quality, Supporting, as soon as possible investment efficiency. Since 1981, a total of 13,300 gates have been installed globally. Among them, 5,400 were opened in 1983. Three years to build 74.2 kilometers of cable duct, the new trunk