论文部分内容阅读
在1990年4月召开的全国重点建设工作会议上,首次提出并决定对国家重点建设项目进行后评价。随后,国家计委在京召开了国家重点建设项目后评价工作会议,对十四个重点建设项目的后评价工作进行了部署。兖州矿务局的鲍店矿井被列为煤炭行业第一个后评价项目;兴隆庄选煤厂经主管部门同意,也列入后评价计划,与鲍店矿井的后评价同时进行。经过七个多月的紧张工作,于1990年10月完成了这两个项目的自我评价阶段的工作,分别提出了两个项目的《后评价报告》。同年12月17~22日,受国家计委的委托,中国国际工程咨询公司邀请了十几位专家,与能源部、中国统配煤矿总公司、山东省煤炭公
At the national key construction work conference held in April 1990, it was the first time that a post evaluation of key national construction projects be made and decided. Subsequently, the State Development Planning Commission held a post-evaluation meeting of key state construction projects in Beijing and deployed post-evaluation work on 14 key construction projects. Yanzhou Mining Bureau of Bao shop mine was listed as the coal industry’s first post-evaluation project; Xinglongzhuang coal preparation plant agreed by the competent authorities, but also included in the post-evaluation plan, and Bao shop after the mine appraisal at the same time. After more than seven months of intense work, the self-evaluation phase of the two projects was completed in October 1990 and the “post-evaluation reports” of the two projects were put forward respectively. In the same year December 17 ~ 22, commissioned by the State Planning Commission, China International Engineering Consulting Corporation invited a dozen experts, and the Ministry of Energy, China National Coal Mine Corporation, Shandong Province Coal Company