为解决火电厂建筑施工中垂直运输的需要,水电部杭机所在测绘引进设备的基础上,根据国内材料、电气元件及配套设备的生产情况,进行了1.5吨附壁式(人货两用)升降机的设计,6月21日至23日水电部制造局在杭州主持召开了施工设计审定会。参加单位有部基建司、各省市电建公司以及三门峡水工机械厂。会议审定认为该升降机设计合理,其性能与引进的同类产品基本一致。由于采用齿轮—
In order to solve the need for vertical transportation in the construction of thermal power plants, the Ministry of Water Resources and Hydroelectric Engineering incorporated the equipment for mapping and mapping, and based on the production of domestic materials, electrical components, and ancillary equipment, 1.5 tons of attached wall type (person and cargo) The design of the lifts, June 21st to 23rd, the Ministry of Water Resources and Manufacturing Bureau presided over the construction design certification meeting in Hangzhou. Participating units include the Ministry of Infrastructure, provincial and municipal electricity construction companies, and Sanmenxia Hydraulic Machinery Plant. The meeting approved that the lift was designed to be reasonable and its performance was basically the same as that of similar products introduced. Due to the use of gears -