我国所用的网络方法多是依据CPM法或PERT法来进行编制的.这种方法的特征是工序间的逻辑关系为紧密衔接的,也就是紧前工序完成之后,紧后工序才可以开始工作,在紧前工序与紧后工序之间,即不必要表示停歇,也不允许出现塔接现象.可是当有些工序之间不允许紧接着进行后续工作,而要求有一定时间的技术停歇或组织间断时.则就需要把这种停歇或间断时间列为不需要劳动力或消耗资源而仅占有时间的工序,把这种工序同样列
Most of the network methods used in China are compiled based on the CPM method or the PERT method. The characteristics of this method are that the logical relationships between processes are closely linked, that is, after the completion of the immediate process, the next process can be started. Between the immediately preceding process and the immediately following process, that is, it does not necessarily mean that there is a stop, and tower connection is also not allowed. However, it is not allowed to perform follow-up work between some processes, and it requires a certain amount of time for technical stoppage or organization interruption. At this time, it is necessary to classify this stop or break time as a process that does not require labor or consumption of resources but only time.