2012年3月28日,三门核电站首个500 kV送出工程—三门核电—回浦500 kV双回输电线路工程进行首例基础试浇,标志该工程全面开工。这是浙江省2012年首条开工的500 kV输电线路。三门核电500 kV送出工程远景规划新建500 kV线路95.4 km。三门核电—回浦线路工程为送出线路工程一期工程,起于浙江台州三门核电厂,止于500 kV回浦变变电站,全长47.4 km。一期工程计划于2013年6
On March 28, 2012, the first basic trial pouring of the 500 kV transmission project at Sanmen NPP - Sanmen NPP - HuiPu 500 kV double circuit transmission line project marks the full commencement of the project. This is the first 500 kV transmission line started in Zhejiang in 2012. Sanmen Nuclear Power 500 kV Transmission Project Long-range Planning Newly Built 500 kV Transmission Line 95.4 km. Sanmen Nuclear Power - Huipu Line Project To send out the first phase of transmission line project, it started from Sanmen Nuclear Power Plant in Taizhou, Zhejiang Province and ends at 500 kV Huupu Substation with a total length of 47.4 km. The first phase of the project is scheduled for 2013 6