日前,历经249天,普洱电网36座35千伏变电站无人值班改造项目全部完成,81座35千伏变电站配合光纤全覆盖工程同步完善远动通信功能。改造工程的顺利实施,不仅大幅提升设备装备水平和自动化水平、提高人员的风险意识和技能素质,实现“改造一批设备,锻炼一批队伍”的目标,也大幅提升供电可靠率,补上了这块长期制约普洱电网安全发展及全面创先的短板。“四步走”层层推进追溯到2012年,普洱局县
Recently, after 249 days, 36 unmanned power transformation projects of 36 35 kV substations in Pu’er Power Grid were completed, and 81 35 kV substations with fiber optic full coverage project simultaneously improved the functions of telecontrol. The smooth implementation of the renovation project not only significantly raised the level of equipment and automation and the level of automation, raised the awareness of risk and quality of personnel, and achieved the goal of “transforming a batch of equipment and training a batch of teams”, but also greatly improved the reliability of power supply, On this piece of long-term constraints Pu’er power grid security development and create a comprehensive short. “Four steps to go” layers of promotion dating back to 2012, Pu’er County